11.0 Inspection of Site


11.1  The Contractor shall be deemed to have inspected and examined the Site and its surroundings and to have satisfied hiself before submitting his tender as to the following : 

(a) the nature of the ground and subsoil ; 
(b) the form and nature of the Site 
(c) the extent and nature of the work, material and goods necessary for the completion of the Works; 
(d) the means of communication with and access to the Site 
(e) the accommodation he may require; and 
(f) in general to have obtained for hijmself all necessary information as to risks, contingencies and all circumstances influencing and affecting his tender. 

11.2  Any information or document forwarded by the Government to the Contractor shall not relieve the Contractor of his obligations under the provisions of this clause. 